The short answer
First apply to RAC for a Declaration of No Objection. After installation, UOOW and Aqualectra inspect the electrical work, grid connection and protection settings. Submit the approved inspection card, VvGB and connection documents to Aqualectra. Feed-in only starts after approval and agreement.
The procedure in six checks
- Before installationVvGB bij RAC
- Recognised supervisionUOOW E-installateur
- InspectionUOOW + Aqualectra
- After approvalKeuringskaart + overeenkomst
- Feed-inPas na contract en meter
- RecheckProcedure vlak vóór indienen
![[object Object]](https://curacao.day/api/cw?w=beeld&u=https%3A%2F%2Fcommons.wikimedia.org%2Fwiki%2FSpecial%3AFilePath%2FInstallation%20of%20photovoltaic%20modules%20on%20roof.jpg%3Fwidth%3D1280)
Step 1 is design and documentation by the owner and PV installer. Before installation, RAC assesses the system, inverter, any batteries and technical information. The current RAC form says inspection must be supervised by an electrical installer recognised by UOOW.
Step 2 is applying to RAC for the VvGB. RAC currently says the form cannot be completed or submitted digitally; deliver it in person or by post to Beatrixlaan 9 marked ‘Aanvraag Verklaring van Geen Bezwaar’. Recheck immediately before submission.
Step 3 is construction to the approved design. UOOW then inspects the PV and home or business installation as an extension; Aqualectra checks the grid connection and protection settings. The recognised electrical and PV installers attend unless a valid authorisation is used.
Step 4 is the stamped inspection card. Rejection produces a defects list and blocks connection until reinspection. Next submit the application, connection agreement, VvGB and remaining documents to Aqualectra. Feed-in can only be settled after the agreement and correct metering/grid connection.
What is the order for solar with feed-in in Curaçao?
Design → RAC VvGB before installation → build → UOOW/Aqualectra inspection → stamped inspection card → connection agreement and documents to Aqualectra → metering/grid connection, then settlement.