Connecting solar in Curaçao: VvGB, UOOW and Aqualectra in the right order

The official procedure starts with RAC before installation. UOOW and Aqualectra inspect next; only after an approved inspection card comes grid connection and feed-in.

The procedure in six checks

Step 1 is design and documentation by the owner and PV installer. Before installation, RAC assesses the system, inverter, any batteries and technical information. The current RAC form says inspection must be supervised by an electrical installer recognised by UOOW.

Step 2 is applying to RAC for the VvGB. RAC currently says the form cannot be completed or submitted digitally; deliver it in person or by post to Beatrixlaan 9 marked ‘Aanvraag Verklaring van Geen Bezwaar’. Recheck immediately before submission.

Step 3 is construction to the approved design. UOOW then inspects the PV and home or business installation as an extension; Aqualectra checks the grid connection and protection settings. The recognised electrical and PV installers attend unless a valid authorisation is used.

Step 4 is the stamped inspection card. Rejection produces a defects list and blocks connection until reinspection. Next submit the application, connection agreement, VvGB and remaining documents to Aqualectra. Feed-in can only be settled after the agreement and correct metering/grid connection.

What is the order for solar with feed-in in Curaçao?

Design → RAC VvGB before installation → build → UOOW/Aqualectra inspection → stamped inspection card → connection agreement and documents to Aqualectra → metering/grid connection, then settlement.

Ask

Ask me anything5 questions today

Comments

Know more or see it differently? Your comment goes up right away.

More articles

All numbers and foreign press →
Street Art Curacao 2018
Mural · WillemstadPhoto: ImagePerson / CC BY 4.0

Free · 1 tap · stop anytime